Student Affairs Relocation Schedule

The following departments and organizations have (or will) move to a temporary location to better serve students during the renovation, with the exception of the Gregg Museum, which will find its permanent home in the former Chancellor's residence on Hillsborough Street. Most organizations will be found in Harrelson Hall, which is located in the Brickyard.

Please refer to the chart below for move specifics. Plans are subject to change, so please check back often.

Name of Department

Move Date

Move Location

ARTS NC STATE (Miller) & Student Programs (Reiman) Business Office 

Late 2013

Harrelson 2nd Floor

ARTS NC

  • AVC Miller, AVC Exec. Assistant , Center Stage & Arts Outreach, Dance Program, Arts Development,  Arts Marketing

Late 2013

New Talley - Phase I

ARTS NC STATE- Gregg Museum of Art & Design

Late 2013

516 Brickhaven Drive

AVC  for Student Affairs (Reiman)

Late 2013

Harrelson 303

Campus Activities

NOW IN HARRELSON

Harrelson 217

Chaplains' Cooperative Ministry

NOW IN HARRELSON

Harrelson 362

Catering & Reservations

Late 2013

New Talley -   Phase I

CSLEPS

NOW IN HARRELSON

Harrelson 344

GLBT Center

NOW IN HARRELSON

Harrelson 360

NASA- Native American Student Assoc.

NOW IN HARRELSON

Harrelson 312

NC State Bookstores

NOW IN HARRELSON

Harrelson Ground Level

Parents & Families Services- PFS

December 2011

Harrelson 111

Student Affairs Technology Services

December 2012

Harrelson 117

Student Centers Board of Directors

Talley 3134 (main) &

Harrelson 213 (satellite)

Student Government

NOW IN HARRELSON

Harrelson 355

Student Organization & Involvement Center

NOW IN HARRELSON

Harrelson 103

Ticket Central

Late 2013

Thompson Hall

Union Activities Board

NOW IN HARRELSON

Harrelson  206

University Dining

Late 2013

New Talley  – Phase I

University Student Legal Services

NOW IN HARRELSON

Harrelson 337

University Theatre

  • June 2011
  • Late 2013
  • Talley 1200
  • Thompson Hall

Women's Center

NOW IN HARRELSON

Harrelson 322

Notes:

  • These dates are subject to change.
  • Departments staying in Talley throughout the renovation and expansion are shaded in gray.
  • Moves that occur together are color-coded the same color.
  • Moves that may occur together depending on remarks column are given the same date +/- (e.g.: paint & carpet must be completed first.

Key

image 1Moving Beginning of June                  image 2   Moving mid- June

image 3  Moving in December                    image 4   Moving into  Phase I Talley

image 5  Late 2013