Alexander Hall will experience intermittent vibration through the end of the Spring Semester as the building foundation is secured prior to Phase I construction related to the Talley Student Center.
We continue to install chilled water lines down Cates Avenue and are turning north on Jeter Drive. We are nearly complete with Phase I electric and telcomm duct banks in front of Case, and we are approximately 30 percent complete with new steam line installation along West Cates Avenue (in front of Price and Talley.
To receive construction alerts via email, send a message to newtalley@lists.ncsu.edu with SUBSCRIBE in the subject line.