North Carolina State University and U.S. Bank Combine Campus ID and Prepaid MasterCard, ATMs on Campus

RALEIGH, N.C.  and MINNEAPOLIS, MINN.  (April 18, 2012) – North Carolina State University (NC State)  and U.S. Bank have partnered to offer the Wolfpack One Card, a campus identification card that doubles as a prepaid MasterCard® card, to the incoming freshmen class in June 2012.  Current students, faculty or staff members can upgrade starting in


NC State ID Card/Office Gets New Name

RALEIGH, NC (April 18, 2012) – The NC State AllCampus Card office — and its ID card — have been renamed Wolfpack One, it was announced today by Dr. Dan Adams, associate vice chancellor for Campus Enterprises.  The name change was precipitated by a new relationship with U.S. Bank that will enable two debit account

web banner

Atrium Food Court Renovation Honored

University Dining awarded gold in the Loyal E. Horton Dining Awards May 4, 2012 (Raleigh, NC) — University Dining at NC State University was awarded Gold in the Loyal E.Horton Dining Awards by the National Association of College and University Food Services (NACUFS) for the Atrium Food Court Renovation.  NACUFS annually awards food service organizations

Talley Construction Update: May 3, 2012

Reduced Construction Work Hours Contractors will continue a reduced work schedule through Thursday, May 10th (last day of finals) for the heavy equipment. Work hours will be 9am-8pm and contractors will resume the 7am start Friday May 11th. After graduation and residence hall move out on May 12th, contractors will begin summer hours. Work includes:

Talley Construction Update: April 26, 2012

A couple general updates this week in addition to the past and next 7 days schedule. Study Rooms Available in Talley With the fire separation walls complete on the 3rd floor, the study rooms and lounge (formerly CSLEPS, Campus Activities and Parents & Families Services offices) have been reopened. There are 6 rooms plus lounge

Talley Construction Update: April 19, 2012

Schedule: Past 7 Days Existing Talley 1. Completed the 3rd and 4th floor separation walls 2. Completed the east side temporary stair erection (by Reynolds) 3. Cut the northeast building column - Blog post on the process: Digging a Little Deeper – Column Shoring and Extension 4. Started the north stairwell separation walls North of Talley –

Fryer Oil to Tractor Fuel

NC State Students Transform Campus with University Dining RALEIGH, N.C. (April 18, 2012) – North Carolina State University engineering students are taking used fryer oil from two campus dining facilities and converting it into biodiesel fuel which is then being used in a variety of tractors and other off-road equipment. NC State’s Biofuel Research and

Talley Construction Update: April 5, 2012

Construction activity continues to increase. This includes activity at the Cates Avenue construction entrance. Please use caution when walking around the site and past construction entrances. Schedule: Past 7 Days Existing Talley 1. Completed the 2nd floor precast demolition 2. Completed the 2nd floor temporary corridor walls and ceiling 3. Continued the 3rd floor and

Talley Construction Update: March 16, 2012

Schedule: Past 7 Days Existing Talley 1. Completed the demolition of the Ballroom Storage Wall (the brick wall you could see from the exterior NE Corner) 2. Continued the 2nd floor 2-hour corridor wall 3. Completed the 3th floor abatement 4. Continued on the 4th-floor demo and abatement 5. Completed the lighted exit sign relocation in

Talley Construction Update: March 8, 2012

Schedule: Past 7 Days Existing Talley  1. Installed the 2-hour fire separation wall in the Wolves’ Den restaurant and construction office 2. Removed asbestos and demolished the 2nd floor soffit 3. Removed asbestos and began demolition of the ballroom storage room 4. Completed the column wrap demolition for the temporary shoring (steadying) and stair on